Thursday, 6 December 2007

More Photos

The UFH - not much to show for over 3 grand! A bit of swirly red piping and the manifold from the previous post. This was the 23rd November.

The screed company let us down on the saturday. The driver didn't turn in so no delivery but no-one told our guys so everyone was hanging around waiting. Eventually we found out and after some argy bargy, Martin's screed guy got onto Tarmac for a delivery monday afternoon... and here it is. Monday 26th.


Luverly and smooth - trouble is a dog got in chasing our cat overnight and got footprints right across here!! Geoff got rid fo the worst of them near the front door but we'll have some sanding and filling to do when it's done. This stuff is Tarmac Truflo.

Now the floor cost another £2K. We were going to use normal sand and cement screed but a few things swayed us. Firstly, we can turn the heating on after 3 days with this stuff - it's 3 WEEKS with the sand and cement - and we have no other heating downstairs. Secondly, we want Karndean flooring on top and that needs a smooth surface - so hopefully we'll save a few quid not needing the floor levelling (well - apart from the dog prints that is!). Lastly, this is the recommended screed for UFH as being liquid it runs round the pipes and you're not supposed to get cold spots. Unfortunately, what is not supposed to happen is the floor to get very wet.... then we had 80mph winds and torrential rain all weekend, the temporary roofing got blown off and we had 1/2inch of standing water. Geoff made temporary repairs on sunday and on monday finished most of the roof so Sarah and Stephen mopped up and it's been virtually dry since - we still have a bit of a leak around the Velux so a bit more work to do but it's coming.

By the friday Geoff had got us some stairs and on the saturday we moved back in.... hmm..
Here is a slightly dark picture of the main room. The shuttering is where the new doorway will be, but until the uPVC company and Geoff agree which order the rear porch roof is getting done in, we have no doorway as such....

Piccies

Well, finally managed to hook up the big PC and transfer the photos from the camera. We don't have a wide angle lens so it's hard to photograph the big room, but when I get a chance in daylight I'll try and do a panorama shot again.


18th november 9am



18th November 4pm20th November (yes the fridge has been moved!):

All the insulation ready to go in on top of the new slab - 150mm of the stuff!!! (20th November)

Concrete! 20th November

A hole for the pipes into the island.
Tanking on top of the insulation ready for the UFH pipework (23rd November)
The UFH manifold. Water comes in top left (the valves are the wrong colour on this picture!) and goes back to the boiler bottom left and is distributed to the heating zones from all the verticals.