Thursday 27 March 2008

Post Easter Update

Well, not enough has happened....

We have a plastered and skimmed upstairs hallway, and the big cupboard on the landing (which forms one side of the bath alcove) has been built and boarded ready for skimming; the washing machine is finally plumbed in - no more trips to the launderette.... - but that's it. No kitchen, still a room full of tools and still a huge list of little things to 'finish off' everywhere.

We have booked the flooring contractor for the 7th April to lay the Amtico downstairs. The only issue is really the cupboard in front of the UFH manifold, but we can allow for that if we have to. There are still a couple of holes in the floor where the old electric meter was and some little gaps near the walls in a couple of places but they won't take long.

What is annoying is the pace - we are so close now, but it is taking forever. The fridge got unpacked yesterday and the the gap was plasterboarded so once that is skimmed the fridge can go in - but the plug might not be live so we still may not be able to use it.

On the good news, the bathroom tiles should be in today or tomorrow so they should start tiling next week with a bit of luck.....