Friday, 14 September 2007

Yet another hole, a roof and some windows....

Well, another hole appeared and disappeared over weds and thurs. This is the back door and Rob has removed the existing single skin outside wall and is running the new double-skin wall up to the joint with the utility room. The wall will be thicker so we'll have to work out what to do inside.


Rob and Geoff battening the rear roof. You can see two of the three Velux windows - one arrived with a damaged frame so the roof has stopped until that gets delivered (weds) and the guys can finishing battening between the windows then start tiling. We are going for new Brazilian slate apparently!


Here is the whole house again. The Velux will have the usual grey outer when they're done, but they have a white inner as the ceiling will be white. The main roof has been delayed. Our building regs drawings specified no floor in the loft and standard computer designed joists. Geoff asked if we wanted a traditional roof which would give us more space inside which of course we said yes to, as we wanted to walk around... 'Ah, you want a floor'... So back to Howard the structural engineer for some re-calcs - a traditional roof uses the side walls to carry load so he has to check the ground floor RSJs are upto it... Another delay. Useful Geoff spotted the design issue - just wish we had all spotted it earlier so we weren't waiting on Howard. Once the calcs are back, Geoff can order the roof materials and get it up. Once that is tiled, the glass can go in everywhere (the windows are ordered) and we'll be weather tight - time to ask the bank for more money!

Friday, 7 September 2007

The whole house

Some slightly ropey photos today. Here is the whole rear of the house. You can see the full scale of the extension at the right of the house


Here you can see the front of the house. The window lintel isn't on yet, but should be up tomorrow.
Rob is now here full time bricking and Geoff has him working on the front and gable walls so the main roof can go on soon. We need Howard the structural engineer to work out whether the RSJ along the side of the house is up to the job if we go for a traditional roof (as Geoff suggests) rather than a modern truss job. The trusses would sit on the front and rear walls whereas a traditional roof will load the side walls as well. Once we know the loadings, RSJ sizes and cost comparison we'll decide which roof to go for and Geoff can order it straight away to put it up (hopefully) the week after next. Then we should see the glass going in and the extension made water tight (excluding the porch). Time to get the valuer back and get the next load of money! £12K left at the moment.

Next door have also got into the act with a dormer (and a similar side extension later on)....



Tuesday, 4 September 2007

Roof

The rear roof has been built now - you can see the outlines of the 3 Velux windows across the roof. Next step is the felt and batten (I believe), then the felt is cut to insert the Velux flashings, then the tiles, then the windows themselves


This is the new rear porch. Rob is having some fun building the pillars either side of the door as they are quite small. We may consider using a conservatory corner - with uPVC panels instead of bricks/blocks - we need to check if we can do it.


Geoff is back from holiday on Thursday. Time to talk about the time to get the main roof up and the windows in - then we get the valuer back and try and get some more money out of the bank. Also time to see if it's time to get the new boiler and tank installed. The new boiler is gas and nPower want £350 to do their bit of the gas supply, we'll need to excavate and run the rest of the pipe to the house and install the box, and nPower will fit the meter. Hopefully we can plumb the new boiler/tank into the existing rads and hot water supply then we can see about getting the old boiler and the oil tank removed.

Tuesday, 21 August 2007

Window lines

Here is the rear of the first floor. You can see the outline of the bathroom window on the left - we have lost about 3 courses of bricks at the bottom of it for the new roof. You can also the master bedroom window - this is now 7 inches wider at the left after we had the outer leaf of brick removed. You can also see the ground floor door/window opening with the CATNIC beam bricked in. Also on the left is the new opening from the extended rear porch into the house.


Plenty more beams waiting to be installed - These are for the first floor windows. I think there is still one more to come as we have the bathroom, master bedroom, en-suite and front bedroom windows.

This is the front elevation - the bedroom window is getting to lintel height.

Geoff is going to order the roof this week, so hopefully it will start going up next week sometime. Hoorah!

Thursday, 16 August 2007

Busy(ish) week

Well, I was off work this week to help Sarah look after the kids. The builders have made steady if unspectacular progress this week. Lots of scaffolding and lots of labouring for Pete getting blocks and bricks up the scaffold for Rob to lay them.

The front and rear first floor walls have some definition now with openings for the windows - the one at the back looked huge at first. Also, The extension is tied into the house on top of the beams now so it looks like one house, not two (These were taken yesterday):

The beam for the rear windows/doors is sat on the brickwork and lets you see the size of the opening - although it looks quite low, Pete has 8 inches headroom, and he's 6'2".

This will be our dressing room (or spare bedroom) window. It is offset as the en-suite is tucked in the left hand corner.



The whole thing - you can see the en-suite window on the gable wall and the tying in at the front.

This was mid-day today:
There are two more courses of brick, a damproof membrane and a couple more courses of brick on top of the blockwork on the beams - more piccies tomorrow when it stops raining! The bedroom window has been boarded up as well now - it's like the black hole of Calcutta in there.